| Start Date and Time | What was worked on | Stop Date and Time | Total Time | Running Time |
| 760:00:00 | ||||
| 5/10/2002 18:30 | Set up all new tools, cut and drilled gusset block clamps. Tapped them and put in bolts. Made 62 Clamps | 5/10/2002 22:30 | 04:00 | 4:00 |
| 5/11/2002 10:45 | Clean up shop | 5/11/2002 11:20 | 00:35 | 4:35 |
| 5/11/2002 12:15 | Clean up shop | 5/11/2002 13:50 | 01:35 | 6:10 |
| 5/11/2002 13:50 | Inventory of Spruce order from Wicks | 5/11/2002 14:35 | 00:45 | 6:55 |
| 5/11/2002 14:35 | Work Bench Upgrade | 5/11/2002 15:45 | 01:10 | 8:05 |
| 1/0/1900 14:35 | Layout plans on bench | 1/0/1900 15:45 | 01:10 | 9:15 |
| 5/11/2002 16:45 | Start cutting spruce for fuselage sides; start framing fuselage side 1 | 5/12/2002 3:30 | 10:45 | 20:00 |
| 5/12/2002 14:00 | Framing Fuselage Side 1 | 5/12/2002 17:30 | 03:30 | 23:30 |
| 5/17/2002 20:15 | Framing Fuselage Side 1 | 5/17/2002 22:15 | 02:00 | 25:30 |
| 5/18/2002 20:15 | Outline framed fuselage on bench and prepped for epoxy | 5/18/2002 22:15 | 02:00 | 27:30 |
| 5/18/2002 13:10 | Mixed one oz of epoxy and glued stations A,B, C and D | 5/18/2002 14:15 | 01:05 | 28:35 |
| 5/18/2002 14:50 | Prepped next section for epoxy | 5/18/2002 15:00 | 00:10 | 28:45 |
| 5/18/2002 15:00 | 1/4 Oz epoxy to glue stations E, F and G (side 1) | 5/18/2002 15:40 | 00:40 | 29:25 |
| 5/18/2002 15:40 | Prepped next section for epoxy | 5/18/2002 16:10 | 00:30 | 29:55 |
| 5/18/2002 16:10 | 1 Oz epoxy to glue stations H, I, J, K, L, M, N | 5/18/2002 17:10 | 01:00 | 30:55 |
| 5/27/2002 13:10 | Prepped Fuselage Side 2 | 5/27/2002 14:10 | 01:00 | 31:55 |
| 5/27/2002 18:00 | Prepped Fuselage Side 2 | 5/27/2002 20:15 | 02:15 | 34:10 |
| 5/31/2002 22:05 | Prepped Fuselage Side 2 | 5/31/2002 22:35 | 00:30 | 34:40 |
| 6/3/2002 18:10 | Final prep for side 2 for epoxy | 6/3/2002 18:30 | 00:20 | 35:00 |
| 6/3/2002 20:55 | Epoxy side 2 | 6/3/2002 23:35 | 02:40 | 37:40 |
| 6/4/2002 19:40 | Removed side 2, gusset blocks and sanded down table | 6/4/2002 20:30 | 00:50 | 38:30 |
| 6/9/2002 12:10 | Clean up shop | 6/9/2002 12:50 | 00:40 | 39:10 |
| 6/9/2002 12:55 | Sand Fuselage side 1 | 6/9/2002 13:55 | 01:00 | 40:10 |
| 6/9/2002 14:00 | Sand Fuselage side 2 | 6/9/2002 15:10 | 01:10 | 41:20 |
| 6/9/2002 15:10 | Prep for plywood | 6/9/2002 15:55 | 00:45 | 42:05 |
| 6/9/2002 16:05 | Put plywood on frame sides | 6/9/2002 20:30 | 04:25 | 46:30 |
| 6/9/2002 19:30 | Pull Staples out of plywood Side 1 | 6/9/2002 20:25 | 00:55 | 47:25 |
| 7/13/2002 17:05 | Prepare and laminate center spar caps | 7/13/2002 18:20 | 01:15 | 48:40 |
| 7/14/2002 17:00 | Prepare and laminate center spar caps | 7/14/2002 17:25 | 00:25 | 49:05 |
| 7/16/2002 22:40 | Prepare and laminate outer spar caps | 7/16/2002 23:10 | 00:30 | 49:35 |
| 7/20/2002 16:45 | Prepare and laminate outer spar caps | 7/20/2002 17:10 | 00:25 | 50:00 |
| 7/20/2002 19:00 | Pull Staples out of plywood Side 2 | 7/20/2002 19:30 | 00:30 | 50:30 |
| 7/21/2002 15:00 | Prepare and laminate outer spar caps | 7/21/2002 15:25 | 00:25 | 50:55 |
| 7/21/2002 15:55 | Trim plywood on sides | 7/21/2002 19:35 | 03:40 | 54:35 |
| 7/22/2002 17:15 | Prepare and laminate outer spar caps | 7/22/2002 18:00 | 00:45 | 55:20 |
| 7/27/2002 17:00 | Dimension Spar caps | 7/27/2002 17:20 | 00:20 | 55:40 |
| 7/27/2002 17:20 | Dimension vertical tail post | 7/27/2002 20:20 | 03:00 | 58:40 |
| 10/26/2002 20:15 | Prepare fuselage sides | 10/26/2002 20:30 | 00:15 | 58:55 |
| 10/26/2002 21:45 | Fuselage and Wing plywood saddle gussets installed | 10/26/2002 23:45 | 02:00 | 60:55 |
| 10/27/2002 11:45 | Saddle gussets | 10/27/2002 12:30 | 00:45 | 61:40 |
| 10/28/2002 21:15 | Trim ends of fuselage for vertical tail post | 10/28/2002 22:00 | 00:45 | 62:25 |
| 11/3/2002 23:29 | Set up jig to set up fuselage on table | 11/3/2002 23:59 | 00:30 | 62:55 |
| 11/9/2002 22:29 | Laminate 1/4" plywood to tail post | 11/9/2002 23:59 | 01:30 | 64:25 |
| 11/10/2002 0:01 | Frame fuselage on table | 11/10/2002 1:46 | 01:45 | 66:10 |
| 11/10/2002 10:00 | Prepare Jig and clean workshop | 11/10/2002 12:30 | 02:30 | 68:40 |
| 11/10/2002 15:30 | Prepare Jig and clean workshop | 11/10/2002 19:00 | 03:30 | 72:10 |
| 11/10/2002 21:00 | Prepare rear tail post and clean workshop | 11/11/2002 2:45 | 05:45 | 77:55 |
| 11/11/2002 8:30 | Fix broken longeron | 11/11/2002 12:00 | 03:30 | 81:25 |
| 11/11/2002 19:00 | Dimension Spar caps | 11/11/2002 19:15 | 00:15 | 81:40 |
| 11/11/2002 21:50 | Dimension Spar caps | 11/11/2002 22:30 | 00:40 | 82:20 |
| 11/16/2002 13:00 | Frame fuselage on table | 11/16/2002 16:00 | 03:00 | 85:20 |
| 11/16/2002 16:00 | Fix broken longeron | 11/16/2002 18:30 | 02:30 | 87:50 |
| 11/17/2002 11:50 | Frame fuselage on table | 11/17/2002 12:20 | 00:30 | 88:20 |
| 11/19/2002 23:30 | Frame fuselage on table / Pull ends of fuselage together | 11/20/2002 1:00 | 01:30 | 89:50 |
| 11/21/2002 21:30 | Lower engine mount rail and compression brace; cut spruce for boat and epoxy in place | 11/21/2002 23:30 | 02:00 | 91:50 |
| 11/22/2002 22:00 | Cut spruce for boat bottom (B) | 11/22/2002 22:30 | 00:30 | 92:20 |
| 11/22/2002 23:25 | Cut spruce for boat bottom (C,E,F,H,I,J) | 11/23/2002 0:50 | 01:25 | 93:45 |
| 11/23/2002 10:30 | Tape cross members for epoxy and epoxy | 11/23/2002 12:50 | 02:20 | 96:05 |
| 11/23/2002 22:15 | Remove tape from previous step | 11/24/2002 1:30 | 03:15 | 99:20 |
| 11/24/2002 21:05 | Make gussets for bottom of boat and epoxy in place | 11/25/2002 2:45 | 05:40 | 105:00 |
| 11/25/2002 21:25 | Prep bottom for plywood | 11/25/2002 23:10 | 01:45 | 106:45 |
| 11/25/2002 23:55 | Finish prep and scarf plywood for bottom of boat | 11/26/2002 2:55 | 03:00 | 109:45 |
| 11/26/2002 22:30 | Cut plywood for bottom of boat to size, fit and epoxy tail post to boat | 11/27/2002 2:15 | 03:45 | 113:30 |
| 11/27/2002 15:50 | Sand Tail post | 11/27/2002 16:05 | 00:15 | 113:45 |
| 11/27/2002 22:15 | Epoxy bottom skin (plywood) to boat--Helped by Kevin and Dad | 11/28/2002 0:30 | 02:15 | 116:00 |
| 11/28/2002 15:30 | Thanksgiving day--removed staples from bottom of boat | 11/28/2002 16:00 | 00:30 | 116:30 |
| 11/28/2002 19:30 | Trimmed bottom skin to match sides of boat | 11/28/2002 20:00 | 00:30 | 117:00 |
| 11/28/2002 20:30 | Sand sides and bottom of boat | 11/28/2002 22:10 | 01:40 | 118:40 |
| 11/28/2002 22:30 | Epoxy voids in plywood (bottom of boat to bottom from of fuselage) | 11/28/2002 23:50 | 01:20 | 120:00 |
| 11/29/2002 13:35 | Remove staples, clean up epoxy cups and sand | 11/29/2002 14:00 | 00:25 | 120:25 |
| 11/29/2002 20:15 | Prepare to remove boat from table and flip rightside up | 11/29/2002 22:00 | 01:45 | 122:10 |
| 11/29/2002 22:35 | Prepare and epoxy upper ?? ?? And aux top longerons | 11/30/2002 1:00 | 02:25 | 124:35 |
| 11/30/2002 12:45 | Remove clamps and start firewall pieces and prep | 11/30/2002 15:00 | 02:15 | 126:50 |
| 11/30/2002 15:40 | Prepare rear stringers (cross braces) | 11/30/2002 17:00 | 01:20 | 128:10 |
| 11/30/2002 19:55 | Make more gussets | 11/30/2002 21:00 | 01:05 | 129:15 |
| 11/30/2002 22:00 | Make more gussets | 11/30/2002 22:50 | 00:50 | 130:05 |
| 11/30/2002 23:00 | Make more gussets and epoxy (J, K, L, M, N) | 12/1/2002 1:15 | 02:15 | 132:20 |
| 12/1/2002 23:40 | Remove clamps and epoxy station I | 12/2/2002 0:50 | 01:10 | 133:30 |
| 12/2/2002 22:30 | Fit and epoxy upper engine mount doubler | 12/3/2002 0:00 | 01:30 | 135:00 |
| 12/3/2002 22:20 | Braces for plywood brace for firewall (fit and epoxy) | 12/4/2002 0:00 | 01:40 | 136:40 |
| 12/4/2002 22:30 | Side plywood firewall brace (2.5 mil birch) cut / fit / brace | 12/5/2002 0:15 | 01:45 | 138:25 |
| 12/5/2002 23:25 | Draw firewall in Auto cad | 12/6/2002 2:45 | 03:20 | 141:45 |
| 12/6/2002 22:15 | Firewall plywood shelf (bottom of top shelf) | 12/7/2002 0:45 | 02:30 | 144:15 |
| 12/7/2002 16:35 | Firewall under plywood shelf braces | 12/7/2002 17:55 | 01:20 | 145:35 |
| 3/1/2003 16:30 | Sanding front of firewall level | 3/1/2003 17:30 | 01:00 | 146:35 |
| 3/6/2003 21:30 | Odds and ends (sanding of excess epoxy on fuse) (scratching head to prepare for spar build) | 3/6/2003 23:00 | 01:30 | 148:05 |
| 3/7/2003 20:45 | Center Front Spars | 3/8/2003 0:15 | 03:30 | 151:35 |
| 3/8/2003 13:00 | Front center spar cleanup and start rear center spar | 3/8/2003 15:05 | 02:05 | 153:40 |
| 3/8/2003 22:00 | Scarf and cut plywood for center spar and epoxy to Rear center spar | 3/9/2003 0:05 | 02:05 | 155:45 |
| 3/9/2003 12:45 | Remove rear spar from jig and sheet side 1 of front center spar | 3/9/2003 14:25 | 01:40 | 157:25 |
| 3/11/2003 15:00 | Paint insides of both center spars | 3/11/2003 15:45 | 00:45 | 158:10 |
| 3/11/2003 22:10 | Tail wheel filler block | 3/11/2003 23:00 | 00:50 | 159:00 |
| 3/11/2003 23:10 | Second coat of spar varnish to both center spars | 3/11/2003 23:40 | 00:30 | 159:30 |
| 3/12/2003 13:00 | Firewall parts | 3/12/2003 14:40 | 01:40 | 161:10 |
| 3/12/2003 20:50 | Plywood spar skins and epoxy center front spar | 3/12/2003 23:00 | 02:10 | 163:20 |
| 3/13/2003 13:20 | Epoxy rear center spar side two plywood web | 3/13/2003 15:10 | 01:50 | 165:10 |
| 3/13/2003 17:25 | Cut out spar slots for front center spar on fuselage | 3/13/2003 18:50 | 01:25 | 166:35 |
| 3/13/2003 21:00 | Fit Center Spar in fuselage | 3/13/2003 22:25 | 01:25 | 168:00 |
| 3/13/2003 23:15 | Cut wing templates | 3/14/2003 2:40 | 03:25 | 171:25 |
| 3/14/2003 11:15 | Airfoil templates and sand front center spar to airfoil shape | 3/14/2003 16:45 | 05:30 | 176:55 |
| 3/14/2003 19:50 | Airfoil templates | 3/14/2003 23:00 | 03:10 | 180:05 |
| 3/15/2003 0:20 | Airfoil templates and level fuselage | 3/15/2003 1:30 | 01:10 | 181:15 |
| 3/31/2003 23:00 | Aileron Bellcrank fabrication | 4/1/2003 1:20 | 02:20 | 183:35 |
| 4/1/2003 21:15 | Bellcrank parts | 4/2/2003 0:40 | 03:25 | 187:00 |
| 4/5/2003 15:30 | Anodize parts (scrap parts to test colors and process) | 4/5/2003 23:15 | 07:45 | 194:45 |
| 4/7/2003 22:15 | Polish aileron parts | 4/7/2003 23:00 | 00:45 | 195:30 |
| 4/9/2003 22:00 | Cut parts out of 2.5" X 4" aluminum angle | 4/9/2003 23:40 | 01:40 | 197:10 |
| 4/10/2003 21:15 | Aileron Parts | 4/10/2003 23:00 | 01:45 | 198:55 |
| 4/13/2003 17:20 | Control Stick Parts | 4/13/2003 18:00 | 00:40 | 199:35 |
| 4/15/2003 21:40 | Control Stick Parts | 4/15/2003 23:10 | 01:30 | 201:05 |
| 4/18/2003 13:00 | Aileron parts (anodize and assemble bellcrank parts) | 4/19/2003 1:00 | 12:00 | 213:05 |
| 4/19/2003 14:00 | Anodize metal parts (elevator/control stick brackets) | 4/20/2003 4:45 | 14:45 | 227:50 |
| 4/20/2003 16:00 | Rebuild big table and clean garage | 4/21/2003 0:00 | 08:00 | 235:50 |
| 5/20/2003 21:15 | Practice Glass layups | 5/20/2003 23:30 | 02:15 | 238:05 |
| 5/27/2003 21:15 | Practice Glass layups | 5/27/2003 22:30 | 01:15 | 239:20 |
| 5/28/2003 17:50 | Practice Glass layups | 5/28/2003 18:10 | 00:20 | 239:40 |
| 5/28/2003 21:30 | Practice Glass layups | 5/28/2003 23:55 | 02:25 | 242:05 |
| 5/29/2003 20:15 | Practice Glass layups | 5/29/2003 21:30 | 01:15 | 243:20 |
| 8/16/2003 22:15 | Tail wheel spring layup | 8/16/2003 23:55 | 01:40 | 245:00 |
| 8/17/2003 17:00 | Cut carbon rod for tailwheel spring | 8/17/2003 17:15 | 00:15 | 245:15 |
| 8/17/2003 22:00 | Tail wheel spring layup | 8/17/2003 23:10 | 01:10 | 246:25 |
| 8/18/2003 21:30 | Tail wheel spring layup | 8/18/2003 22:05 | 00:35 | 247:00 |
| 8/19/2003 22:00 | Tail wheel spring layup | 8/19/2003 22:40 | 00:40 | 247:40 |
| 9/13/2003 20:45 | Put tubes into tires and mount on rims | 9/13/2003 21:15 | 00:30 | 248:10 |
| 9/13/2003 22:00 | tail wheel bracket #1 | 9/14/2003 0:40 | 02:40 | 250:50 |
| 9/14/2003 14:00 | tail wheel bracket #1 | 9/14/2003 15:10 | 01:10 | 252:00 |
| 12/24/2003 21:00 | Sand landing gear legs | 12/24/2003 21:30 | 00:30 | 252:30 |
| 12/26/2003 17:30 | Sand landing gear legs | 12/26/2003 17:50 | 00:20 | 252:50 |
| 12/26/2003 18:30 | Prep to epoxy glass to legs | 12/26/2003 19:00 | 00:30 | 253:20 |
| 12/26/2003 19:00 | Leg 1 epoxy glass to leg | 12/26/2003 20:00 | 01:00 | 254:20 |
| 12/27/2003 15:00 | Prep and epoxy glass to leg 1 | 12/27/2003 16:30 | 01:30 | 255:50 |
| 12/27/2003 20:45 | Mark and drill left gear bracket | 12/27/2003 21:15 | 00:30 | 256:20 |
| 12/28/2003 15:00 | brake tubes glassed to both legs | 12/28/2003 17:00 | 02:00 | 258:20 |
| 12/28/2003 18:30 | Drill right gear bracket | 12/28/2003 19:00 | 00:30 | 258:50 |
| 12/28/2003 19:30 | Drill axle casting holes 2 of 8 | 12/28/2003 21:45 | 02:15 | 261:05 |
| 12/29/2003 14:00 | Drill axle casting holes 6 of 8 and 8 of 8 on second leg | 12/29/2003 17:30 | 03:30 | 264:35 |
| 1/10/2004 16:00 | Drill holes in casthing for legs and clean garage | 1/10/2004 19:00 | 03:00 | 267:35 |
| 1/10/2004 21:00 | Alignment of legs | 1/10/2004 21:30 | 00:30 | 268:05 |
| 1/10/2004 22:15 | Alignment of legs and drill lower legs for axle casting | 1/10/2004 23:25 | 01:10 | 269:15 |
| 1/11/2004 14:45 | Finish drilling all leg parts | 1/11/2004 17:00 | 02:15 | 271:30 |
| 1/11/2004 21:55 | Drill WAF #1 | 1/11/2004 23:55 | 02:00 | 273:30 |
| 1/12/2004 0:45 | Drill WAF #2 | 1/12/2004 1:40 | 00:55 | 274:25 |
| 1/17/2004 16:00 | Drill WAF # 3&4 on main center spar | 1/17/2004 17:00 | 01:00 | 275:25 |
| 1/17/2004 17:00 | Cut lightning holes in large rib templates | 1/17/2004 19:30 | 02:30 | 277:55 |
| 1/17/2004 19:30 | Fit ribs to spars -- need to work on spars more | 1/17/2004 20:00 | 00:30 | 278:25 |
| 1/18/2004 16:10 | Sand front spar for ribs; put fuse on table and start repare of failed joints | 1/18/2004 17:20 | 01:10 | 279:35 |
| 1/19/2004 12:35 | Prepped two failed joints (tailpost) and cleaned up some others of excess epoxy | 1/19/2004 14:15 | 01:40 | 281:15 |
| 1/19/2004 19:25 | Prep and varnish inside of belly plywood | 1/19/2004 20:50 | 01:25 | 282:40 |
| 1/23/2004 21:30 | Sand excess epoxy (epoxy boogers) | 1/23/2004 22:20 | 00:50 | 283:30 |
| 1/23/2004 22:55 | Sand excess epoxy; level fuse fro main spar insertion | 1/24/2004 0:55 | 02:00 | 285:30 |
| 1/25/2004 14:40 | Fix water level / finish leveling fuse and main spar | 1/25/2004 15:20 | 00:40 | 286:10 |
| 5/17/2004 19:00 | Epoxy rear face of front spar to fuse | 5/17/2004 21:30 | 02:30 | 288:40 |
| 5/18/2004 21:40 | Epoxy front face (outside of fuse) of spar to fuse; epoxy tailpost | 5/18/2004 23:00 | 01:20 | 290:00 |
| 5/26/2004 17:10 | Cut and laminate tailwheel block & wing spar reinforcers | 5/26/2004 17:50 | 00:40 | 290:40 |
| 5/26/2004 21:55 | Cut, trim, fit and epoxy instrument pannel brace and seat brace | 5/26/2004 23:55 | 02:00 | 292:40 |
| 5/28/2004 15:05 | Sand glue joints on cross members; mark location for rear spar | 5/28/2004 15:35 | 00:30 | 293:10 |
| 5/28/2004 18:22 | Sanded spar block; started holes for rear spar | 5/28/2004 18:52 | 00:30 | 293:40 |
| 5/28/2004 20:00 | Finished holes for rear spar; prep spar for airfoil shape | 5/28/2004 23:00 | 03:00 | 296:40 |
| 5/29/2004 18:20 | Sand rear spar to airfoil shape | 5/29/2004 19:20 | 01:00 | 297:40 |
| 5/29/2004 19:25 | Drill 3/8" bolt for tailwheel bearing | 5/29/2004 21:45 | 02:20 | 300:00 |
| 5/29/2004 22:10 | Finished drilling (had to get new drills); epoxy tailwheel block on | 5/29/2004 23:55 | 01:45 | 301:45 |
| 5/30/2004 16:15 | Hone out bolt for tailwheel bearing | 5/30/2004 17:10 | 00:55 | 302:40 |
| 5/30/2004 21:25 | Mount tail spring (temporarily) | 5/30/2004 23:25 | 02:00 | 304:40 |
| 5/31/2004 18:40 | First attempt at welding (tailwheel bracket) | 5/31/2004 20:15 | 01:35 | 306:15 |
| 5/31/2004 21:10 | More welding and clean shop | 5/31/2004 21:30 | 00:20 | 306:35 |
| 6/5/2004 17:45 | Finish airfoil shape on rear spar; drill for 2 WAFs | 6/5/2004 20:25 | 02:40 | 309:15 |
| 6/5/2004 21:45 | Drilled 2 WAFs and fit one of the bell cranks | 6/5/2004 23:45 | 02:00 | 311:15 |
| 6/6/2004 14:10 | 2d Bell Crank | 6/6/2004 15:30 | 01:20 | 312:35 |
| 6/6/2004 17:10 | Rough cut aileron bell crank brackets | 6/6/2004 17:30 | 00:20 | 312:55 |
| 6/6/2004 21:40 | Smooth & start to polish bell crank parts | 6/6/2004 23:50 | 02:10 | 315:05 |
| 7/9/2004 18:15 | Polish Bell crank parts | 7/9/2004 19:00 | 00:45 | 315:50 |
| 7/9/2004 22:00 | Polish Bell crank parts | 7/9/2004 22:15 | 00:15 | 316:05 |
| 7/10/2004 12:50 | Welding practice | 7/10/2004 14:50 | 02:00 | 318:05 |
| 10/11/2004 19:30 | Check level; prep rib templates to epoxy rear spar | 10/11/2004 20:15 | 00:45 | 318:50 |
| 10/13/2004 17:00 | Layout tailwheel bracket | 10/13/2004 17:45 | 00:45 | 319:35 |
| 10/13/2004 20:15 | Cut AL for tailwheel bracket--ready for polish | 10/13/2004 23:00 | 02:45 | 322:20 |
| 10/14/2004 12:15 | Tailwheel bracket (layout and drill three holes) | 10/14/2004 12:55 | 00:40 | 323:00 |
| 10/14/2004 20:45 | Tailwheel bracket (layout and drill two holes) | 10/14/2004 21:00 | 00:15 | 323:15 |
| 10/14/2004 21:40 | Tailwheel bracket (layout and drill final holes) | 10/14/2004 22:10 | 00:30 | 323:45 |
| 10/16/2004 15:00 | Prep, set and expoy rear spar | 10/16/2004 16:30 | 01:30 | 325:15 |
| 10/16/2004 19:45 | Polish tail wheel bracket | 10/16/2004 21:45 | 02:00 | 327:15 |
| 10/17/2004 11:15 | Prep tail wheel bracket for anodizing | 10/17/2004 12:30 | 01:15 | 328:30 |
| 10/17/2004 13:10 | Anodize two pieces of bell crank bracket | 10/17/2004 16:10 | 03:00 | 331:30 |
| 10/17/2004 20:00 | Put next three parts in acid bath; finish polishing first two pieces | 10/17/2004 21:00 | 01:00 | 332:30 |
| 10/17/2004 21:59 | Finish tailwheel assembly; finish anodizing bell crank brackets | 10/17/2004 23:59 | 02:00 | 334:30 |
| 10/18/2004 17:30 | Put gear on (temporarily) and let her sit on her own three feet for first time | 10/18/2004 20:30 | 03:00 | 337:30 |
| 10/22/2004 18:30 | Create second set of front spar reinforcement blocks | 10/22/2004 18:50 | 00:20 | 337:50 |
| 10/22/2004 18:50 | Flox tailwheel spring to fix camber issue | 10/22/2004 19:40 | 00:50 | 338:40 |
| 10/23/2004 13:50 | Tailwheel spring | 10/23/2004 17:10 | 03:20 | 342:00 |
| 10/23/2004 17:15 | Right front spar reinforcment wedges installed | 10/23/2004 18:45 | 01:30 | 343:30 |
| 10/24/2004 15:45 | Right rear bottom spar braces | 10/24/2004 16:45 | 01:00 | 344:30 |
| 10/24/2004 22:25 | Right rear top spar braces | 10/24/2004 23:15 | 00:50 | 345:20 |
| 10/25/2004 16:50 | Left front and rear, top and bottom rear spar braces | 10/25/2004 18:50 | 02:00 | 347:20 |
| 10/25/2004 20:15 | Tapering station N for elevator spar braces | 10/25/2004 21:45 | 01:30 | 348:50 |
| 10/26/2004 19:50 | 1st attempt at bearing blocks for rudder peddels | 10/26/2004 21:20 | 01:30 | 350:20 |
| 10/27/2004 22:35 | 2d attempt (final) at bearing blocks for rudder peddels | 10/27/2004 23:50 | 01:15 | 351:35 |
| 10/28/2004 21:40 | Set up epoxy pumps for West system epoxy; reinforce firewall members | 10/28/2004 23:15 | 01:35 | 353:10 |
| 10/30/2004 20:25 | Fix break in fuse (because ply web is not installed); cut 4130 for rudder pedel | 10/30/2004 23:55 | 03:30 | 356:40 |
| 10/31/2004 0:05 | Cut 4130 tubing for second rudder pedel and weld both | 10/31/2004 2:05 | 02:00 | 358:40 |
| 10/31/2004 12:30 | Taper tailpost and re-atatch to fuse | 10/31/2004 15:00 | 02:30 | 361:10 |
| 10/31/2004 15:50 | Dress and re-weld rudder pedels; install spruce reinforcment for rudder pedels | 10/31/2004 21:10 | 05:20 | 366:30 |
| 11/1/2004 17:35 | Drill rudder pedel bearing blocks and fuse to match; put foam between (for under 1/4" floor plywood) | 11/1/2004 20:00 | 02:25 | 368:55 |
| 11/1/2004 21:35 | cut and epoxy 1/4" plywood floor from firewall to station B | 11/1/2004 23:55 | 02:20 | 371:15 |
| 11/5/2004 11:00 | Foam B-C and C-D and pour liquid foam in joint | 11/5/2004 11:50 | 00:50 | 372:05 |
| 11/5/2004 14:40 | Reglue B-C (don’t use spray adheasive) | 11/5/2004 14:55 | 00:15 | 372:20 |
| 11/5/2004 19:35 | Sand B-C, remove C-D, glue right rear ply side gusset | 11/5/2004 21:25 | 01:50 | 374:10 |
| 11/6/2004 12:15 | Trim ply side and foam last three bays | 11/6/2004 14:45 | 02:30 | 376:40 |
| 11/8/2004 16:20 | Sand foam last three bays and weigh (104lbs) | 11/8/2004 17:05 | 00:45 | 377:25 |
| 11/14/2004 16:00 | 14 Carbon Fiber gussets | 11/14/2004 17:10 | 01:10 | 378:35 |
| 11/21/2004 13:55 | Epoxy & Fiberglass first lay up on plane (foam in last three bays) | 11/21/2004 16:10 | 02:15 | 380:50 |
| 11/30/2004 21:45 | Tear Down Corvair Block! | 12/1/2004 0:45 | 03:00 | 383:50 |
| 12/2/2004 22:00 | Clean 1 head and polished 2 pushrod tubes | 12/2/2004 23:55 | 01:55 | 385:45 |
| 12/4/2004 20:10 | Finish cleaning all 12 pushrod tubes | 12/5/2004 0:25 | 04:15 | 390:00 |
| 12/5/2004 13:25 | Paint pushrod tubes | 12/5/2004 14:30 | 01:05 | 391:05 |
| 12/5/2004 20:15 | Dissasemble block (remove pistons and open case)--Found Broken Crank! | 12/5/2004 23:15 | 03:00 | 394:05 |
| 12/13/2004 21:20 | Clean Oil and Distributor end of engine | 12/13/2004 23:40 | 02:20 | 396:25 |
| 12/16/2004 21:45 | Remove burrs and flashing | 12/16/2004 23:20 | 01:35 | 398:00 |
| 12/18/2004 19:00 | Remove valves from both heads | 12/18/2004 21:20 | 02:20 | 400:20 |
| 2/13/2005 14:10 | Repaint pushrod tubes, pull head studs out of old block (the one with the broken crank) | 2/16/2005 16:25 | 02:15 | 474:35 |
| 2/13/2005 22:05 | Finish pushrod tubes: polish pushrods and clean head studs | 2/14/2005 0:00 | 01:55 | 476:30 |
| 2/14/2005 15:55 | Removed 6 pistons from connecting rods | 2/14/2005 16:50 | 00:55 | 477:25 |
| 2/14/2005 17:10 | Removed 6 pistons from connecting rods (2d set) | 2/14/2005 17:45 | 00:35 | 478:00 |
| 2/14/2005 18:10 | Clean 2 sets of connecting rods | 2/14/2005 19:30 | 01:20 | 479:20 |
| 2/14/2005 21:00 | Clean and paint 7 head studs and work on oil housing (removed fuel pump boss) | 2/14/2005 22:20 | 01:20 | 480:40 |
| 2/15/2005 16:15 | Mask and paint 5 head studs on case half 1 | 2/15/2005 16:45 | 00:30 | 481:10 |
| 2/15/2005 19:45 | Finish grinding slag off both case halves | 2/15/2005 22:15 | 02:30 | 483:40 |
| 2/16/2005 21:10 | Rough cut front cover from bell housing | 2/16/2005 23:10 | 02:00 | 485:40 |
| 2/17/2005 21:50 | Clean and detail both case halves | 2/18/2005 0:50 | 03:00 | 488:40 |
| 2/18/2005 13:30 | Thread holes, use die on head bolts, clean and paint oil cooler bracket and shape front cover | 2/18/2005 19:00 | 05:30 | 494:10 |
| 2/18/2005 22:45 | Finish front cover and paint | 2/19/2005 1:15 | 02:30 | 496:40 |
| 2/19/2005 12:10 | Work on oil housing | 2/19/2005 13:10 | 01:00 | 497:40 |
| 2/19/2005 17:30 | wash oil housing and block; mask and paint oil housing | 2/19/2005 20:30 | 03:00 | 500:40 |
| 2/20/2005 22:05 | Finish cleaning and mask and paint 1 case half | 2/21/2005 1:35 | 03:30 | 504:10 |
| 2/21/2005 14:10 | Mask and paint studs on case half 1 | 2/21/2005 15:00 | 00:50 | 505:00 |
| 2/21/2005 17:00 | Mask and paint studs on case half 2; remove mask from case half 1 | 2/21/2005 19:55 | 02:55 | 507:55 |
| 2/21/2005 21:00 | Mask studs and paint case half 2 | 2/21/2005 21:30 | 00:30 | 508:25 |
| 2/22/2005 16:20 | Installed 3 head studs with loctite 620 (case half 2) | 2/22/2005 16:40 | 00:20 | 508:45 |
| 2/22/2005 22:20 | Installed last 4 head studs with loctite 620 (case half 2) | 2/22/2005 23:00 | 00:40 | 509:25 |
| 2/25/2005 22:00 | Install foam in one bay of fuse | 2/26/2005 0:40 | 02:40 | 512:05 |
| 2/26/2005 14:10 | Install foam in one bay of fuse | 2/26/2005 16:00 | 01:50 | 513:55 |
| 2/26/2005 21:45 | Work on exhaust stubs; sand bay of fuse | 2/26/2005 23:45 | 02:00 | 515:55 |
| 3/1/2005 21:30 | Clean and debur head 1 | 3/1/2005 23:35 | 02:05 | 518:00 |
| 3/4/2005 22:00 | Prep to install new oil pump | 3/5/2005 1:00 | 03:00 | 521:00 |
| 3/5/2005 13:10 | Install new oil pump; reinstall pressure relief valve | 3/5/2005 16:40 | 03:30 | 524:30 |
| 3/5/2005 17:00 | Firewall corner braces | 3/5/2005 17:30 | 00:30 | 525:00 |
| 3/5/2005 18:15 | Make jig to drill bolt heads | 3/5/2005 18:30 | 00:15 | 525:15 |
| 3/5/2005 18:30 | Create firewall template; epoxy four firewall corner braces | 3/5/2005 22:35 | 04:05 | 529:20 |
| 3/6/2005 11:50 | Finish firewall template; start instrument panel template | 3/6/2005 13:50 | 02:00 | 531:20 |
| 3/6/2005 15:20 | Finish instrument panel template | 3/6/2005 16:10 | 00:50 | 532:10 |
| 3/6/2005 16:40 | Prep to make forward deck | 3/6/2005 17:45 | 01:05 | 533:15 |
| 3/6/2005 20:20 | Foam and sand front deck; added plaster | 3/7/2005 1:20 | 05:00 | 538:15 |
| 3/7/2005 11:45 | Front deck extention | 3/7/2005 12:30 | 00:45 | 539:00 |
| 3/7/2005 19:00 | Front deck extention | 3/7/2005 21:10 | 02:10 | 541:10 |
| 3/7/2005 21:10 | Drill three engine bolts and clean 1 rocker arm | 3/7/2005 22:00 | 00:50 | 542:00 |
| 3/9/2005 20:15 | Mark and cut 3 layers of BID and 1 layer of deck cloth for front deck | 3/9/2005 21:15 | 01:00 | 543:00 |
| 3/9/2005 21:30 | Glass layup for front deck (practice piece) | 3/9/2005 22:30 | 01:00 | 544:00 |
| 3/10/2005 11:30 | Remove front deck and carve groves for hat stringers | 3/10/2005 12:35 | 01:05 | 545:05 |
| 3/10/2005 21:50 | Tape groves and epoxy stringers to skin | 3/11/2005 0:40 | 02:50 | 547:55 |
| 3/21/2005 21:20 | Cut out first part of engine assembly stand (building jig) | 3/21/2005 23:30 | 02:10 | 550:05 |
| 3/22/2005 15:50 | Welded side 1 of engine assembly jig and drill holes in base of side 2 | 3/22/2005 16:30 | 00:40 | 550:45 |
| 3/22/2005 21:45 | More welding on engine assembly jig | 3/23/2005 0:45 | 03:00 | 553:45 |
| 3/23/2005 12:30 | Weld side 2 of engine assembly stand | 3/23/2005 12:50 | 00:20 | 554:05 |
| 3/23/2005 16:40 | Finish welding engine assembly stand | 3/23/2005 17:40 | 01:00 | 555:05 |
| 3/23/2005 20:30 | Prepare case and join; plastiguage crank; install crank and cam | 3/24/2005 1:00 | 04:30 | 559:35 |
| 3/24/2005 11:50 | Plastiguage rod bearing | 3/24/2005 12:30 | 00:40 | 560:15 |
| 3/24/2005 19:40 | Final case half assembly on engine stand | 3/24/2005 21:50 | 02:10 | 562:25 |
| 3/25/2005 23:10 | Clean and paint cylinders | 3/26/2005 2:10 | 03:00 | 565:25 |
| 3/26/2005 13:40 | Final paint cylinders; install rings on pistons; coat oil in cylinders | 3/26/2005 15:15 | 01:35 | 567:00 |
| 3/26/2005 19:20 | Put pistons in cylinders | 3/26/2005 20:50 | 01:30 | 568:30 |
| 3/26/2005 21:50 | Put Cylinders in block | 3/27/2005 1:40 | 03:50 | 572:20 |
| 3/27/2005 12:20 | Put 3 studs in oil housing end of motor; finished drilling bolts for front cover; installed front cover seal | 3/27/2005 13:55 | 01:35 | 573:55 |
| 3/27/2005 15:25 | Install front cover on motor | 3/27/2005 16:25 | 01:00 | 574:55 |
| 3/27/2005 21:00 | Rip out test front deck | 3/27/2005 21:10 | 00:10 | 575:05 |
| 3/28/2005 17:45 | Shop cleanup | 3/28/2005 21:40 | 03:55 | 579:00 |
| 3/29/2005 21:25 | Replace instrument panel brace with new one; work on reverse templates for front deck | 3/29/2005 23:50 | 02:25 | 581:25 |
| 3/30/2005 21:55 | Finish form for front deck and glue in foam | 3/31/2005 0:20 | 02:25 | 583:50 |
| 3/31/2005 19:00 | Sand foam in front deck reverse template | 3/31/2005 20:30 | 01:30 | 585:20 |
| 3/31/2005 21:50 | Finish sanding and glass inside tront turtle deck | 3/31/2005 23:35 | 01:45 | 587:05 |
| 4/1/2005 22:15 | Remove and fit front turtle deck on fuse | 4/1/2005 23:30 | 01:15 | 588:20 |
| 4/6/2005 20:10 | Check for sizes of AN Bolts needed for prop hub (AN 34); paint ring gear | 4/6/2005 21:45 | 01:35 | 589:55 |
| 4/8/2005 21:30 | Checking out and trial fit prop hub | 4/8/2005 22:30 | 01:00 | 590:55 |
| 4/10/2005 15:50 | Remove piston/cylinder assemblies (I originally put them in the wrong order) | 4/10/2005 17:30 | 01:40 | 592:35 |
| 4/10/2005 20:15 | Re-install cylinders 5 & 6; install oil plugs | 4/10/2005 21:20 | 01:05 | 593:40 |
| 4/11/2005 13:20 | Re-install cylinders 1 - 4 | 4/11/2005 14:30 | 01:10 | 594:50 |
| 4/11/2005 19:20 | Install rear housing and harmonic balencer; prep oil cover | 4/11/2005 21:20 | 02:00 | 596:50 |
| 4/12/2005 13:25 | Hinges for front deck | 4/12/2005 14:25 | 01:00 | 597:50 |
| 4/12/2005 19:20 | Hinges for front deck | 4/12/2005 20:20 | 01:00 | 598:50 |
| 4/20/2005 16:40 | Front Deck | 4/20/2005 17:25 | 00:45 | 599:35 |
| 4/20/2005 21:25 | Epoxy front deck to hinges | 4/20/2005 21:55 | 00:30 | 600:05 |
| 5/4/2005 21:50 | Tailwheel | 5/4/2005 22:05 | 00:15 | 600:20 |
| 5/6/2005 17:15 | Ring gear/pully assembly; seal the motor to store until heads get back from WW | 5/6/2005 18:45 | 01:30 | 601:50 |
| 5/6/2005 18:45 | Cut out real firewall | 5/6/2005 20:45 | 02:00 | 603:50 |
| 5/6/2005 20:45 | Sand front deck | 5/6/2005 22:30 | 01:45 | 605:35 |
| 5/7/2005 12:20 | Finish sanding and prep front deck for glass | 5/7/2005 13:30 | 01:10 | 606:45 |
| 5/7/2005 14:20 | Glass front deck | 5/7/2005 17:05 | 02:45 | 609:30 |
| 5/7/2005 19:10 | Start Seat | 5/7/2005 20:10 | 01:00 | 610:30 |
| 5/7/2005 20:30 | Weld washers on control stick assembly | 5/7/2005 22:35 | 02:05 | 612:35 |
| 5/8/2005 14:30 | Build jig to weld control stick assembly | 5/8/2005 17:00 | 02:30 | 615:05 |
| 5/8/2005 20:10 | Weld control stick assembly | 5/8/2005 21:00 | 00:50 | 615:55 |
| 5/8/2005 22:00 | Weld control stick assembly | 5/9/2005 0:10 | 02:10 | 618:05 |
| 5/9/2005 18:30 | Clean shop | 5/9/2005 20:00 | 01:30 | 619:35 |
| 5/9/2005 20:30 | Prep and glass side 1 of seat (carbon fiber); layup test sample for rudder pedel | 5/9/2005 22:30 | 02:00 | 621:35 |
| 5/10/2005 16:50 | Prep seat bottom for lips and prep to lay down floor | 5/10/2005 19:50 | 03:00 | 624:35 |
| 5/10/2005 22:10 | Cut carbon fiber for floor and seat lips; epoxy seat lips | 5/11/2005 0:20 | 02:10 | 626:45 |
| 5/15/2005 16:25 | Control Stick | 5/15/2005 17:25 | 01:00 | 627:45 |
| 5/15/2005 21:05 | control Stick | 5/15/2005 21:25 | 00:20 | 628:05 |
| 5/16/2005 20:35 | Al welding practice | 5/16/2005 23:00 | 02:25 | 630:30 |
| 5/17/2005 21:55 | Install carbon fiber floor board | 5/17/2005 23:30 | 01:35 | 632:05 |
| 5/18/2005 11:55 | Foam forward fuse (2 panels left side) | 5/18/2005 12:25 | 00:30 | 632:35 |
| 5/18/2005 21:30 | Foam over spars; install rudder peddles | 5/18/2005 23:00 | 01:30 | 634:05 |
| 5/21/2005 13:00 | Remove foam from last 5 bays; glue left rear side plywood panel on | 5/21/2005 17:30 | 04:30 | 638:35 |
| 5/31/2005 15:25 | Cut Carbon Fiber for seat bottom | 5/31/2005 16:40 | 01:15 | 639:50 |
| 5/31/2005 21:25 | Glass bottom of seat with carbon fiber | 5/31/2005 22:25 | 01:00 | 640:50 |
| 6/2/2005 15:40 | Carbon fiber layups for rudder peddles and canopy hinges | 6/2/2005 17:25 | 01:45 | 642:35 |
| 6/3/2005 19:00 | Seat back and rudder peddles | 6/3/2005 22:20 | 03:20 | 645:55 |
| 6/4/2005 15:10 | Seat hinges and seat back | 6/4/2005 19:40 | 04:30 | 650:25 |
| 6/4/2005 21:00 | Epoxy glass tape to sides and top of seat; pull staples from fuse side; remove tape from seat hinges; sand front deck | 6/5/2005 0:00 | 03:00 | 653:25 |
| 6/5/2005 14:25 | Bottom edges of seat | 6/5/2005 17:05 | 02:40 | 656:05 |
| 6/5/2005 20:00 | Hinges to bottom of seat; laminate horizontal stabalizer spars | 6/5/2005 23:30 | 03:30 | 659:35 |
| 6/6/2005 18:20 | Cut hinges for H-Stab; flox and tape inges on seat; draw H-Stab spars | 6/7/2005 0:00 | 05:40 | 665:15 |
| 6/7/2005 16:30 | Clean and install seat back; mark to cut in half | 6/7/2005 17:00 | 00:30 | 665:45 |
| 6/9/2005 21:30 | Control stick | 6/9/2005 23:30 | 02:00 | 667:45 |
| 6/13/2005 18:20 | Control Stick | 6/13/2005 23:20 | 05:00 | 672:45 |
| 6/14/2005 15:35 | control Stick | 6/14/2005 16:55 | 01:20 | 674:05 |
| 6/14/2005 20:30 | control Stick | 6/14/2005 23:05 | 02:35 | 676:40 |
| 6/19/2005 12:00 | H-Stab spars cut to shap (at dads shop) | 6/19/2005 13:00 | 01:00 | 677:40 |
| 6/27/2005 18:45 | Trial fit canopy; spray-lat canopy (used brush) | 6/27/2005 20:35 | 01:50 | 679:30 |
| 7/1/2005 16:00 | Spray-lat inside of canopy (brushed on) | 7/1/2005 16:30 | 00:30 | 680:00 |
| 7/1/2005 16:30 | Cut and weld new rudder pedles; start on brake pedels | 7/1/2005 23:30 | 07:00 | 687:00 |
| 7/2/2005 13:30 | Rudder Pedles; brake supports | 7/2/2005 16:30 | 03:00 | 690:00 |
| 7/2/2005 19:40 | Re-inforce rudder peddle brackets with glass tape | 7/2/2005 22:00 | 02:20 | 692:20 |
| 7/3/2005 18:30 | Work on canopy (trial fit); prepare and glass 4' X 2' X 2" plyfoam | 7/3/2005 23:15 | 04:45 | 697:05 |
| 7/4/2005 10:10 | Canopy frame | 7/4/2005 13:45 | 03:35 | 700:40 |
| 9/6/2005 9:40 | Canopy frame | 9/6/2005 11:30 | 01:50 | 702:30 |
| 9/10/2005 9:30 | Canopy frame | 9/10/2005 11:30 | 02:00 | 704:30 |
| 9/10/2005 13:10 | Horizontal Stabalizer Hinges | 9/10/2005 15:00 | 01:50 | 706:20 |
| 9/10/2005 16:10 | Horizontal Stabalizer Hinges | 9/10/2005 16:40 | 00:30 | 706:50 |
| 9/10/2005 16:40 | Canopy frame | 9/10/2005 17:30 | 00:50 | 707:40 |
| 9/19/2005 18:40 | Canopy frame | 9/19/2005 19:25 | 00:45 | 708:25 |
| 9/25/2005 13:00 | Epoxy rear canopy brace in | 9/25/2005 15:30 | 02:30 | 710:55 |
| 10/9/2005 12:10 | Front Deck Canopy Extention for Canopy Frame | 10/9/2005 16:50 | 04:40 | 715:35 |
| 10/10/2005 14:00 | Trim and mount Canopy (Frame "Plan B" | 10/10/2005 18:30 | 04:30 | 720:05 |
| 10/12/2005 16:10 | Flap Motor (take apart old cordless drill) | 10/12/2005 17:30 | 01:20 | 721:25 |
| 10/22/2005 11:00 | Layup CF instrument panel | 10/22/2005 13:05 | 02:05 | 723:30 |
| 11/5/2005 15:40 | Canopy frame | 11/5/2005 18:10 | 02:30 | 726:00 |
| 11/6/2005 12:30 | Glass Canopy Frame | 11/6/2005 16:45 | 04:15 | 730:15 |
| 11/9/2005 21:00 | Spread MICRO on canopy frame | 11/9/2005 21:45 | 00:45 | 731:00 |
| 11/10/2005 11:30 | Rear Canopy Brace (Frame around aft part of canopy) | 11/10/2005 17:30 | 06:00 | 737:00 |
| 11/11/2005 10:15 | Rear Seat Brace (1/4" plywood behind seat); canopy frame; aft deck hinges | 11/11/2005 18:15 | 08:00 | 745:00 |
| 11/12/2005 12:30 | Roll Bar; rear template for Rear Deck | 11/12/2005 18:00 | 05:30 | 750:30 |
| 11/12/2005 22:15 | Roll Bar | 11/13/2005 1:30 | 03:15 | 753:45 |
| 11/13/2005 15:30 | Sanded bottom of Roll Bar flush with sides; Glued templates to canopy hinge carbon fiber sheet (5 layers of CF with 4 pieces of 3/32" balsa) | 11/13/2005 17:00 | 01:30 | 755:15 |
| 11/14/2005 17:00 | Cut out canopy hinges; routed out edges, floxed and put layer of CF around outside edges | 11/14/2005 21:45 | 04:45 | 760:00 |
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 | |||
| 00:00 | 760:00 |